Order No. 1179 amending Order on technical certification for wind turbines.

Country
Type of law
Regulation
Source

Abstract
The Order partly amends Order No. 73, in particular art. 7, whereby commissioning action shall now apply no later than 3 months after all wind turbines have supplied electricity. In article 10 and Appendix 2, the amendment applies to the word windmill which is now amended to wind turbine with rotor area of 40 square meters . In Appendix 3 the amendment applies to 40 square meters which now reads 200 square meters .
Date of text
Entry into force notes
16 October 2015.
Repealed
No
Source language

English

Legislation status
in force
Legislation Amendment
Yes
Original title
Bekendtg relse om ndring af bekendtg relse om teknisk certificeringsordning for vindm ller.